Street Improvement Projects

Call the Public Works Department at 303-783-2744 for information about street improvement projects.

2018 Chip Seal Project

NOTICE : Cherry Hills Village Public Works has contracted Vance Brothers Inc. to perform Chip Seal Maintenance Operations for the 2018 Capital Improvement Program. Maintenance operations will be performed in the following sub-divisions. Charlou / Chamont sub-division including Charlou Circle, E. Tufts Ave, E. Stanford Ave, and E. Radcliffe Avenue.  Cherry Hills Farms East sub-division including Cherry Hills Farms Drive, Cherry Hills Farms Court, Columbine Court, Fillmore Court, Elizabeth Court, Elizabeth Circle, and Clayton Court. Cherrymoor sub-division including Cherrymoor Drive and S. Vine Way. El Camino north area, including Dasa Drive, Denice Drive, El Camino North Drive, and Charlou Drive (btwn El Camino & Holly).

Barring inclement weather the contractor is scheduled to start this project the week of July 30, 2018. This project should take about two weeks, weather permitting. Mailers have been sent out with more detailed information to all residents who’s address fronts the above mentioned streets. The City will try not to inconvenience our residents any more than necessary to complete this project. For more information you may contact the Public Works Project Manager at 303-783-2741. Thank you in advance for these needed infrastructure repairs. Project Manager Ralph Mason

Holly Belleview Traffic Signals

The City of Greenwood Village is working with CDOT to improve the appearance of the traffic signals at the intersection of Belleview Avenue and Holly Street.  The project consists of removing the existing "span wire" traffic signal poles and installing"standard' traffic signal poles.  These poles will have a similar appearance to the Belleview/University traffic signal but will be painted brown.  Sturgeon Electric is the contractor and will be working in two phases.  The first phase will install all of the underground components of the project including the foundations for the traffic signal poles.  Once the new poles arrive, Sturgeon will return and install the new poles and finally remove the old traffic signal.

There will be temporary lane closures as Sturgeon installs the new traffic signal.  The closures are limited to 9:00 am to 3:00 pm per CDOT requirements.  Later in the year, while installing the new traffic signal poles work will be completed at night.

For questions about the project please call the City of Greenwood Village Public Works Department 303-708-6100.